Date:
Fri, 14 Oct 2005 11:27:10
From:
Michael Furmston
Subject:
Royal Brompton
I
hesitate to intervene in the fascinating discussion about contribution
but the discussion of the Royal
Brompton case may go off on the wrong basis because of
a misunderstanding of the construction contract position. The decision
of the architect as to extensions of time was not dispositive. It
could have been challenged in a subsequent arbitration. In my experience
such decisions are often challenged and often held to be wrong though
more usually where they are in favour of the employer.
The
possible claim against the contractor for delay had been settled
as part of the global settlement. There was a conceivable claim
against the architect that he had negligently granted an unjustified
extension of time. If this could be shown it would damage the employer
by putting him in a worse position in the settlement negotiations
than if the extension had not been given. HL thought this a different
kind of damage from having the building finished late.
Michael
Furmston
<<<<
Previous Message ~ Index ~ Next
Message >>>>>
|