![]() |
RDG
online Restitution Discussion Group Archives |
||||||||||||
![]() |
![]() |
||||||||||||
|
Tang Hang Wu's
"third question" (5/7/99) for me had a relatively simple (contractual) answer.
The issue between the parties seems to be whether the work is covered by
the contract price, or will attract extra payment. The parties agree the
work must be done. They must also be agreeing that, if the umpire says the
work is not covered by the contract price, the builder will be paid extra.
So far, so Alex Axelrod and Steve Hedley (5/10/99). It would be different
if the owner said 'Don't do the work until we get the umpire's decision'
and the builder did it anyway.
Like Gordon Goldberg, I haven't read Cotter.
(Can someone give me a Web address?) What happened? Eoin O'Dell's first
account (5/10/99) says there was no "effective variation of the contract
to cover the extra work done". So I assume the plaintiff went ahead and
did the work anyway, without discussing it with the farmers. If that were
so, it would seem to me not quite enough to say that the plaintiff did
the work on the basis that he was to be paid. He would have answered 'Yes'
to the officious bystander's question 'Is the work to attract extra pay?'
but (particularly having regard to Eoin's disclosure about the finite
amount of money - 5/13/99) the farmers might have answered 'No, not until
you give us a chance to go back to the Minister and negotiate for extra
funds'. They may even have added 'That's why we haven't yet appointed
an Engineer'. But if the plaintiff did go ahead, what then? If he can
get himself 'into' the contract, he will be paid. Steve Hedley (5/13/99)
says the contract did contain an additional remuneration clause, and because
of the parol evidence rule the farmers cannot say otherwise. But if we
are to say the farmers are liable under that clause, its machinery would
have to be followed, or otherwise dispensed with. I personally think it
just complicates things to say the contract would terminate for breach
or frustration (pace Gordon Goldberg) so I would go for some theory that
the condition must be regarded as dispensed with (Mackay v Dick) or that
the court would supply the deficiency (Steven Hedley 5/13/99 citing Sudbrook
Estates). I would probably go for the latter, because I think someone
ought at least to apply their mind to whether the physical conditions
encountered could not reasonable have been foreseen. Further, if there
were no way of dispensing with the machinery, I think I would have to
say that the farmers are not liable. There is a contractual way (the machinery)
for making them liable, there is (by hypothesis) no reason for dispensing
with the machinery, and there seems to me no reason for ignoring the contract
in favour of a restitution solution (accord Eoin 5/10/99 referring to
denial of a restitution remedy where the contract already covers the field).
What if the work was just not contemplated by the contract
at all? For us in Australia, the leading recent case is Update Constructions
Pty Ltd v Rozelle Child Care Centre Ltd (1990) 20 NSWLR 251. Murphy J
in Cotter may have stumbled into restitution (Steve Hedley 5/10/99) but
no-one could say that of Kirby P (as he then was). Priestley JA (Samuels
JA agreeing) found a contractual solution, using estoppel as the means
for overcoming the failure to follow the contract machinery. Tang Hang
Wu may find use in his comments (272-274) on what is 'in' or 'out' of
the contract (including the variation clause) and on the comments in both
judgments on Liebe v Molloy (1906) 4 CLR 347. I would be very interested
in what others have to say about Update. Accepting Steve Hedley's point
(5/13/99) about the resources available in contract analysis, it seems
to me that the more remote we become from what the parties actually agreed,
the more use we might have for a restitutionary analysis that cuts to
the heart of the matter of why we want to do what we end up doing. The
contract techniques may have developed to meet needs at a time when we
didn't think restitution.
Does it make a difference? Not in Update. Alex Axelrod suggests the work
might not be completed. I would have thought the outcome might turn on
how that came about - did the builder down tools, or the owner kick him
off site, or the building burn down? We already have restitution explanations
for what happens in contract (breach by builder, etc.) so it hardly likely
to be different outside contract. There might be a statute which must
be construed as precluding even a restitutionary claim for variations
unless, for example, in writing (Sevastopoulos v Spanos [1991] 2 VR 194)
but we would probably want to construe such a provision as applying to
all variations to the work (contractual or not) as opposed to variations
to the contract. The contract might provide for variations to be paid
for at other than a reasonable rate, but that would be unusual, and unless
the contract were very clear ('you will be paid half the reasonable cost')
we might end up using the contract as evidence of what ought to be paid
by way of restitution. <== Previous message Back to index Next message ==> |
||||||||||||
![]() |
![]() |
» » » » » |
|
![]() |
|||||||||
![]() |